Blog 1 of our Life of Project Series
Every ribbon cutting starts long before the scissors come out. It starts with a vision: a new cultural venue, a restored heritage building, a visitor centre on a fragile stretch of coast. And very often it starts with a funding deadline. How that vision becomes a project, through project initiation, shapes everything that follows.
At Greyfriars, we specialise in client-side project management. We sit on the same side of the table as the councils, trusts, charities and parish councils we serve across Norfolk, Suffolk and the wider East of England, protecting their vision from first idea to final handover. In this series, our team shares what we’ve learnt along the way, stage by stage, following the life of a project from vision to ribbon cutting.
Where we are in the life of a project
We start where every project should: initiation. Projects tend to reach us through one of two doors. Some clients come to us before anything has started, with a vision and a blank page. Others come to us mid-flight, with a programme already under pressure, asking us to get things moving. Both routes need the same foundations, and that’s what this blog is about.

Blog 1 covers RIBA Stages 0 and 1, where PRINCE2’s Starting Up and Initiating processes put the foundations in place.
Why project initiation matters
The decisions made at initiation shape everything that follows. Early on, a change might mean redrafting a brief. Later, the same change can mean redesign, re-procurement or work on site being undone.

That’s why we put so much effort into the first weeks of a project. Time spent getting the business case, governance and controls right at initiation is repaid many times over in design, construction and handover.
Project governance: who’s who, and who decides
Clear governance is the single biggest thing clients underestimate at initiation. When everyone knows who decides what, problems get resolved in days rather than weeks.
PRINCE2 sets out a simple structure, and we tailor it to each client’s own governance rather than bolting on something new:
- Executive / Senior Responsible Owner (SRO): accountable for the project and owner of the business case. SRO is the UK government term; the APM Body of Knowledge calls this role the sponsor. Whatever the name, it should be one person with real authority.
- Senior User: represents the people who will use, run or benefit from the finished project, such as a venue operator, a visitor team or residents.
- Senior Supplier: represents those designing and delivering it, such as the architect, design team or contractor.
- Project Assurance: independent checking, on the board’s behalf, that the project is being run properly.
- Change Authority: the person or group with delegated authority to approve changes within agreed limits.
- Project Manager: runs the project day to day, within the tolerances the board sets.
- Project Support: administration, document control and reporting.
Where does Greyfriars sit?
We work in two ways, depending on what the client needs:

- As the client’s Project Manager, leading delivery day to day and reporting to the project board.
- Alongside an existing client Project Manager, bringing specialist construction, cost management, design and planning expertise to a strong in-house team, and leading a defined workstream such as design and planning.
Both are client-side roles. In both, we’re there to protect the client’s interests, not a designer’s or a contractor’s.
In both models the project board stays with the client; what changes is who leads delivery day to day.
Tolerances and decision rights
Tolerances are the agreed limits of time, cost and scope within which the Project Manager can act without going back to the board. Agree them in writing at initiation. They are what makes management by exception work: the board isn’t drawn into every decision, but nothing significant slips past it.
Who does what at initiation

Common governance pitfalls
Three gaps come up again and again: an SRO without the authority to make decisions, a project board too large to agree anything, and a Senior User who is never consulted until handover.
Our six-step project initiation process
Getting off to the right start is essential. We believe in keeping things straightforward and collaborative, so everyone knows what to expect from day one. Whatever the project, our initiation follows six steps:
- Mobilisation meeting. We bring together the client, the design team and key consultants to confirm the brief, the outputs so far, the programme and the immediate priorities. Where the client has its own project manager, we work closely with them to understand where we can add most value.
- Baseline review. We review the existing information, including cost plans, planning feedback, site and environmental constraints, and project risks. This establishes a clear baseline for the next RIBA stages.
- Programme, reporting and project controls. We set up reporting arrangements, design team meeting schedules, change control and project controls, aligned with the client’s existing governance.
- Consultant and information review. We confirm consultant requirements, survey scopes and the technical information needed to support design development, planning and cost certainty.
- Planning and consents strategy. We review planning requirements, pre-application feedback and consent risks, then set out a clear strategy covering planning, ecology, flood risk, highways and stakeholder engagement.
- Project Initiation Document. Everything from mobilisation is captured in a single Project Initiation Document (PID), defining responsibilities, reporting procedures, programme milestones, risk management and key decision points.
How the six steps map to PRINCE2

Each step does a job PRINCE2 would recognise. The mobilisation meeting confirms the project brief and roles. The baseline review sets the starting point that progress is measured against. Controls and reporting put management by exception into practice, and the consents strategy is risk management by another name. The PID pulls it all into one agreed reference.
What goes in a PID?
The Project Initiation Document (PID) is the single agreed document that the client, the design team and the project manager all work from. In construction you may also hear it called a Project Execution Plan (PEP); the purpose is the same.
A good PID answers five questions:
- Why are we doing this? The business case, the vision and the outcomes.
- Who is responsible for what? Governance, roles and decision rights.
- How will we control it? Reporting, change control, tolerances and the risk register.
- When will things happen? The programme, key milestones and decision points.
- What does success look like? Quality expectations, funder outcomes and handover requirements.
It isn’t a document to file and forget. It’s reviewed at every stage boundary, and updated whenever the project changes significantly.
Two doors into project initiation: early, or at pace
The six steps are the same whichever door a project comes through. What changes is the pace and the order.
Door one: brought in early

This is the ideal. The steps run in sequence, and what we learn feeds straight back into the business case. We can test the brief before design starts, set realistic programme and budget tolerances, bring in early cost advice, and help choose the right procurement route, including frameworks such as ESPO and CGA. Decisions are cheap to change at this point, so this is where the most value is added.
Door two: “we need to get going yesterday”
Sometimes a client comes to us with a programme already running: a funding deadline looming, a design team already appointed, or a project that has lost momentum. PRINCE2’s principle of tailoring to suit the project matters most here. We don’t start again; we compress initiation into a short, focused health check and run the steps in parallel:
- Baseline becomes gap analysis. What governance, programme, budget and risk information already exists, and what’s missing?
- Stabilise before you accelerate. A project board, a reporting rhythm and change control go in first, even in light-touch form.
- The PID records decisions already made, rather than revisiting them, so the team can keep moving.
- Be honest about trade-offs. Expediting a programme usually means accepting more risk, more cost or a narrower scope. The board should choose that knowingly.
- Overlap with care. Running design and procurement in parallel, or engaging a contractor early, can save months, but only when the risks are understood and owned.
Through door two, the steps overlap inside a short health check, so the design team can keep working while governance catches up.
Make the most of it: six things to get right at project initiation
- Appoint your client-side PM early, ideally before your design team, so the brief and procurement route are tested first.
- Name an SRO with real authority. One person, able to make decisions and own the business case.
- Keep the project board small. Executive, Senior User and Senior Supplier, with assurance alongside.
- Agree tolerances in writing, so everyone knows when an issue needs to go to the board.
- Start the risk register on day one, with an owner for every risk.
- If you’re already moving, pause long enough to set up governance. A short health check now saves far more time later.
Next time
The business case stands up, the PID is agreed and the project board is meeting. Then the first design change lands, a risk turns into an issue, and the programme starts to wobble. In Blog 2: The Messy Middle, our team shares how we keep projects on track when reality meets the plan.